manufacturing orders starting date
Topic Started: Jan 20 2018, 06:32 AM (3 Views)
BrianPugh

Hi,
I create a first order; the prod. ord. routing is based on the machine center L3 with capacity 1 run time 2h. So the order start at 8:00am and finish at 10:00am

Then I create a second order based on the same machine center L3; I was expecting the order start date was 10:00 am, instead it is always 8:00am.

Can someone help me to understand how an order starting date works and if I should do somthing else to plan the order start date based on the machine availability?

Please help.
Thanks!

I didn't find the right solution from the Internet.